Project Progress and Pace
See whether the project will finish by its deadline
Project Progress and Pace
The Progress & Pace card on the project overview shows how much of the project is done and whether the current pace is enough to finish by the deadline. It is on every plan.
The chart
- Done (green area): tasks moved to Done over time
- All tasks (grey line): every task of the project over time, so you can see when the scope grew. Archived tasks are left out of every number
- At current pace (green dashed line): where the done line ends on the deadline if the team keeps its pace
- Needed (blue dotted line): the pace that finishes every open task by the deadline
Short projects get a point per week, projects longer than half a year a point per month.
The numbers
- Done: done tasks out of all tasks, with the percentage
- Current pace: tasks done per week over the last 4 weeks (or since the project started, if it is younger). In the first week of a project there is no pace yet and the chart fills in after that week; with a deadline you already see the pace needed
- Needed to finish by the deadline: open tasks divided by the weeks left
- Due in the next 7 days: open tasks with a due date in the coming week
Status
- On track: the current pace is at least the pace needed
- Tight: the current pace is at least 70% of the pace needed
- At risk: the current pace is below 70% of the pace needed
- Overdue: the deadline has passed and tasks are still open
- No deadline: set one in Project Settings to get a forecast
- Just started: the project is younger than a week, so there is no forecast yet
- Complete: every task is done
Overdue and blocked tasks are listed in the Risk Indicators card below.